This article explains the complexities of managing government property, how the audit landscape is tightening, and how modern automation helps maintain compliance.
Why it matters: Government property is listed as one of the military’s 28 Material Weaknesses. Furthermore, Government Property systems are one of the 6 key Contractor Business Systems identified in the DFARS. Failing a property audit can result in withheld payments, formal Corrective Action Plans (CAPs), and out-of-pocket costs for lost or damaged property.
Key Takeaways
- The property business system centers on tracking, not finances: Unlike accounting or procurement systems, a government property management system focuses strictly on tracing the physical lifecycle of government-owned items.
- The FAR clause is the ultimate authority: While other business systems rely on DFARS, property compliance relies directly on FAR 52.245-1 and its “ten property outcomes”.
- Integrated technology brings immense time savings: Connecting automated asset tracking software like A2B Tracking’s UC! Web with Deltek Costpoint can streamline reporting obligations and reduce inventory tracking time by a 30-to-1 ratio.
If you are a federal contractor in possession of government-owned property, you face a unique set of compliance hurdles. Driven by a Department of Defense (DoD) push for a clean financial audit opinion by 2028, regulators are turning an intense spotlight onto how contractors manage physical assets.
In this guide, you will learn the core requirements of a compliant property management system, how DCMA evaluates your risk, and how automated workflows protect your business.
What Is a Government Property Management System?
A Government Property Management system requires federal contractors to establish and maintain an effective setup to appropriately acquire, manage, and use government-owned property in their possession.
While most business systems look closely at accounting and financial figures, a Property system is dedicated entirely to maintaining clear, accurate, and unbroken records of physical property used during contract performance.
With regard to regulations, your primary Government Property framework is provided in FAR 52.245-1, which outlines the responsibilities frequently referred to as the “ten property outcomes” or the property lifecycle. These 10 outcomes define what a contractor’s property management system must achieve functionally.
The 10 Property Outcomes
The FAR clause demands accountability across ten distinct stages of an asset’s lifecycle:
Acquisition: Securing explicit contract authority or a bill of materials before purchasing property with government funds.
Receipt: Inspecting delivered property to verify it is undamaged, accurate, and recorded properly.
Records: Maintaining detailed logs (incorporating roughly 15 specific data points like location and condition) so a complete list can be generated at any moment.
Physical Inventory: Performing periodic inventory counts (with annually being the bare minimum).
Subcontractor Control: Reviewing and auditing your subcontractors to ensure they can mirror the full property lifecycle.
Reports: Promptly providing mandatory reports to the government regarding inventories, excess items, or property loss.
Relief of Stewardship: Securing formal government approval before disposing of or getting rid of any property.
Utilization: Ensuring government property is strictly utilized for its designated contract scope unless authorized otherwise.
Maintenance: Logging and executing regular maintenance on the physical assets.
Property Closeout: Conducting final inventories and processes at the end of the award period.
Sustaining Audit Readiness under DCMA
The Defense Contract Management Agency (DCMA) is tasked with evaluating your system through a Property Management System Analysis (PMSA). The PMSA is the framework that is followed by the DCMA to ensure a thorough and objective review when evaluating a Contractor’s Property Management system. Legally, DCMA aims to conduct an initial audit within 12 months of a contractor first receiving government property.
If your company passes with excellent results, subsequent audits may be spaced out up to a maximum of every four years. However, if deficiencies emerge, follow-up audits can be scheduled rapidly to verify your corrective actions.
DCMA property auditors primarily use two methods:
- Standard Audit: A highly formal, detailed, on-site review involving a formal kickoff, extensive testing, and an exit conference.
- Limited Audit: A remote questionnaire sent via email, featuring sample testing. This format is typically reserved for low-risk, compliant contractors with low-value property. If high-risk answers surface on the questionnaire, DCMA can pivot the review into a standard on-site audit.
DCMA Guidebook for Government Property Administration
The 10 Property Outcomes mentioned earlier provide a high-level definition of a contractor’s property system requirements. However, the DCMA has developed very specific auditing standards to evaluate a contractor’s Government Property management system. The DCMA Guidebook for Government Contract Property Administration provides detailed information into the evaluation methods and processes that an auditor will execute during a Property Management System Analysis (PMSA).
The DCMA Guidebook uses the requirements in FAR 52.245-1 to provide a detailed list of 22 PMSA elements. These 22 elements of a PMSA can be seen as a checklist of mandatory outcomes that DCMA auditors are required to examine during an audit. The elements include: written procedures, self assessments, acquisition, receiving, discrepancies incident to ship, identification, records, receipt and issue, physical inventories, subcontractor award and flow down, subcontractor reviews, reports, relief of stewardship, utilization, declaration of excess, consumption, movement, storage, storage commingling, maintenance, disposal, property closeout.
It’s important to recognize that two of these PMSA elements exist outside of the Property lifecycle, most notably your written procedures and your ongoing internal self-assessments. Contractors must leave a rigorous paper trail confirming they adhere to their own documented policies and procedures. Furthermore, contractors are expected to perform internal audits (self-assessments) on an ongoing basis to ensure compliance.
The Cost of Noncompliance
Similar to any other contractor business systems, there are penalties for non-compliance. The current enforcement environment is growing increasingly strict. This is partially being driven by the National Defense Authorization Act, which is calling for the Pentagon to produce a clean audit opinion by FY2028. This pressure being put on the DoD is trickling down to the government contracting community.
If an audit uncovers significant deficiencies, DCMA can utilize several mechanisms, depending upon the situation, to apply penalties:
- Higher frequency of PMSA reviews
- Increased scrutiny with possible surveillance plans
- Issuing Level 3 Corrective Action Requests (CARs)
- Documentation of poor performance in Contractor Performance Assessment Reports (CPARS)
- Holding your business financially liable out-of-pocket for any lost, stolen, or destroyed property
Ultimately, it is important for organizations to understand their Property Management requirements and the penalties surrounding non-compliance. It’s equally important to have modern technology in place to ensure compliance on an ongoing basis.
How Deltek and A2B Tracking Streamline Property Compliance
Trying to manage extensive property data on disconnected, manual spreadsheets routinely causes frantic fire drills right before an audit. A modern property management system relies on centralized, secure, and automated information pipelines.
By integrating A2B Tracking’s UC! Web platform directly with Deltek Costpoint, defense contractors can benefit from an integrated system that eliminates error-prone manual data entry and builds a sustained audit-ready posture.
Designed to handle complex contract requirements, the joint solution allows for:
- Advanced Automation: Utilizing barcode scanning and RFID technology to replace paper count sheets. Mobile RFID can scan an entire room within seconds. RFID users often see a 30:1 improvement in labor hours (For example, a 30-day manual inventory can be accomplished in a single day with RFID).
- System Integration: Asset information flows seamlessly between Costpoint’s Inventory or Fixed Asset modules and the A2B Tracking’s system.
- Direct Government Reporting: Instead of manually typing updates into government portals, the A2B platform provides a direct connection with PIEE, Wide Area Workflow (WAWF), IUID Registry and the GFP Module to submit lifecycle events securely.
- Security: Supports CMMC demands with secure data storage procedures.
UC! Web is a complete government property management system that ensures full compliance with FAR 52.245-1. It tracks assets through their entire lifecycle with modern barcode and RFID to create a robust asset history. It also provides a secure GEX data exchange with PIEE that provides a confirmation once it’s complete.
This modern Property Management solution integrating Deltek Costpoint and A2B Tracking is purpose-built to simplify the process of tracking, managing and reporting government property, providing the tools your organization needs to pass DCMA audits with confidence.
Learn more about Government Property Management
To take a deeper dive on property management and learn more about the Costpoint A2B Tracking integrated solution. Take a look at this recent webinar which brought together BDO’s Government Property expert Kenzie Davis, Deltek Costpoint’s Solution Engineer Devin Resende and A2B Tracking’s CEO, Peter Collins. The powerful combination of BDO, Deltek and A2B Tracking provides unmatched perspective and expert advice for navigating this complex GovCon space.